First Cask Filled At Unit 4 Fukushima Daiichi

TEPCO announced that they have filled the first cask with fuel as of 6:28PM JST Tuesday. A total of 22 assemblies were loaded between Monday and Tuesday. This from the TEPCO press release via email:

Fukushima, Japan, Nov. 19, 2013-TEPCO announced today that they have completed the second day work for fuel removal from the Unit 4 spent fuel pool at Fukushima Daiichi NPS.
22 fuel assemblies were loaded into the cask, and all the work for the day completed at 6:28PM.”

TEPCO extended work hours of the defueling crews at unit 4 on Tuesday. Shifts will now be 9am to 9pm. On Monday it took about 3.5 hours to move 4 unused fuel assemblies from the pool to the cask. TEPCO had workers move 18 units on Tuesday for a total of 22. The cask will be transferred to the common pool on Wednesday. The fuel currently being handled is unused fuel that was stored in the pool at unit 4.

 

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: