Updated Fukushima Decommissioning Schedule

NHK put out this updated decommissioning schedule for Fukushima Daiichi. It gives an idea how long they assume the project will take as of now. It also shows how work at each unit is being prioritized.

Spent Fuel Removal:
Unit 4: Underway 2013, assumed to be completed 2014
Unit 3: 2015
Unit 2: 2017
Unit 1: 2017

Reactor Fuel Debris Removal:
Unit 4: No reactor fuel
Unit 3: 2021
Unit 2: 2020
Unit 1: 2020

Via: NHK

U1_decommUnit 1 Decommissioning Diagram (TEPCO)

U2decommUnit 2 Decommissioning Diagram (TEPCO)

 

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: