Fukushima Unit 2 Torus Room Inspection

Hitachi GE conducted robot investigations into unit 2’s torus room on July 17th. The main focus of the work was to look at the pipe penetrations between the torus room wall and the turbine building. The swimming and also the crawling robots did the work together. It was noted that the layer of debris and sediment in the bottom of the torus room caused some problems when the robots kicked up that sediment. Other earlier torus room inspections found considerable layers of sediment on the torus room floors.

Tracer was used to see if the pipes between the torus room and the turbine building were leaking around the penetration seals. It didn’t appear to have any significant flow either direction. A more detailed set of work was documented on this inspection compared to unit 1. Here they explained the use of sonar to inspect the area. Images and a diagram below.

Handout from TEPCO in English
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2014/images/handouts_140728_05-e.pdf

u2_torusroom_140728_01 u2_torusroom_140728_02 u2_torusroom_diagram

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: