Radiation Spike At Fukushima Daiichi Discharge Canal
A significant spike in contaminated water levels at Fukushima Daiichi in the unit 1 discharge canal was reported today. Readings between Feb 14th and Feb 18th saw a considerable jump beyond normal fluctuations for these two locations. The only new work began between the 14th and 18th is the concreting of the unit 4 seawater piping trench. It is not clear if this had any influence on the readings or if so, why it would.
Feb 18th
Near Unit 1 Near outlet
C-134 3,800 C-134 580
C-137 13,000 C-137 2,000
Beta 20,000 Beta 8,200
Near Unit 1 Near outlet
C-134 3,200 C-134 480
C-137 11,000 C-137 1,700
Beta 14,000 Beta 3,500
Near Unit 1 Near outlet
C-134 3,300 C-134 540
C-137 11,000 C-137 1,800
Beta 14,000 Beta 3,700
Near Unit 1 Near outlet
C-134 3,300 C-134 490
C-137 11,000 C-137 1,700
Beta 15,000 Beta 3,600
Near Unit 1 Near outlet
C-134 3,300 C-134 520
C-137 11,000 C-137 1,700
Beta 15,000 Beta 3.400
Near Unit 1 Near outlet
C-134 3,100 C-134 450
C-137 10,000 C-137 1,700
Beta 14,000 Beta 3,500
Daily reports including floodway readings: http://www.tepco.co.jp/nu/fukushima-np/handouts/index-j.html
This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org
© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved
Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.