Fukushima Unit 2 Containment Inspection Delayed To January
TEPCO announced that the problems created by the stuck shielding blocks and high radiation in the work area will require the containment inspection to be delayed until January 2016. Rusted shielding blocks caused ongoing delays as they tried to determine a way to remove them. The area also has radiation levels as high as 1 sievert/hour. This has prevented workers from being in the area for any extended time.
NHK reports that human workers were used to operate a piece of heavy equipment to dislodge the blocks. They worked in shifts with a large amount of physical shielding attached to the heavy equipment unit to help lower worker exposures. NHK reported the workers received 2.5 millisieverts of external exposure each for their work.
The long delay is due to the need to decontaminate the work area before human workers can enter. There is already a series of robots used on site for decontamination, these will likely be used to attempt to lower the radiation dose.
This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org
© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved
Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.