As part of the efforts by the government and METI to improve the contaminated water problem at Fukushima Daiichi new tanks have been being installed. Some tanks were welded together on site. A new set of tanks is being prefabricated elsewhere and shipped to the plant for installation.

The pre-assembled tanks are put together and shipped by barge to the plant where they are transferred by crane to a flat bed trailer and driven to the tank area for installation. Where the factory is located is said to possibly be in Kobe, Mitsubishi has some involvement as indicated by the banner on one of the tanks pictured.

The process can be seen in the photos below. Two handouts were distributed on the project.
http://www.tepco.co.jp/nu/fukushima-np/handouts/2014/images/handouts_140417_05-j.pdf
http://www.tepco.co.jp/nu/fukushima-np/handouts/2014/images/handouts_140417_07-j.pdf

140417_01 140417_02

140417_03 140417_04 140417_05 140417_06 140417_07

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: