TEPCO Finally Repairs Unit 5 Spent Fuel Pool Cooling

After weeks of unit 5 not having an operational spent fuel pool cooling system, TEPCO has finally replaced the leaking valve. The valve interior showed considerable corrosion that lead to the leak. TEPCO failed to explain why it took them so long to repair the system. While the repair was delayed the spent fuel pool and reactor vessel that still contains fuel had to share the reactor cooling system.

Unit 5 is the second newest reactor at the plant. This incident does raise questions about the stability and corrosion of other systems in the older units. Leaks and failures could cause additional challenges as they attempt to remove damaged fuel from the older units. Reactor monitoring showed the spent fuel pool of unit 5 going back into a cooler more stable state over the last two days.

u5_rpv_cooling_july_31_2014 Reactor vessel temps

u5_sfp_temps_july_31_2014 Spent fuel pool temps

unit5_valve_replace_140730_01 Old valve removed

unit5_valve_replace_140730_02 Corrosion within the old valve

unit5_valve_replace_140730_03 New replacement valve

unit5_valve_replace_140730_04 Pipe internal condition

unit5_valve_replace_140730_05 New valve installed

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: