Unit 1 Cover Removal Begins At Fukushima Daiichi
Initial work to remove the cover off unit 1 at Fukushima Daiichi has begun. The initial work includes cutting a hole into the tent cover and spraying a fixative to try to lower dust releases.
Actual removal is scheduled for next year with demolition work falling further into 2016. The unit is currently scheduled for spent fuel removal in 2017.
http://www.tepco.co.jp/nu/fukushima-np/handouts/2014/images/handouts_141022_06-j.pdf
This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org
© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved
Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.