The Big Job To Sample Water At A Fukushima Vent Stack
The effort to deal with the unit 1-2 vent stack has grown in complexity. TEPCO claims in this new work that the radiation levels near the tower are so high that it is complicating work. A mock up facility was built to practice the work before the actual on site work took place.
The goal of this latest work is to determine the water level in the sump, the water composition and to collect the sump water using remote equipment.
Preparation work began around July 28, 2016 to do this work.
A crawler robot was used to open the tower drain pit around August 26th.
Actual pumping work is expected to take place in early to mid September 2016.
A pump and hose run to the waste processing building would handle the water. They then intend to flush the hose towards the waste handling building to remove remaining highly radioactive water.
At the end of the work a water meter will be installed. If this follows other monitoring added around the plant, it would signal workers if the water level in the pit exceeded a set level.
TEPCO reports can be found here and here, images and diagrams of the work below:
Close up of the drain pit.
Access area and wide view of the work area. Note the thick shielding placed on one side.
Large view of the work area.
Diagram of the robotic sampling process for the drain pit.
Mock up and test run of the work to sample the drain pit.
This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org
© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved
Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.