SimplyInfo.org; TEPCO Shows Fatal Reactor Design Flaw At Fukushima Daiichi

An inspection of Fukushima Daiichi unit 2 in June of 2021 shows a fatal design flaw of the BWR reactors that may have contributed to their destruction.

The inspection conducted was of the reactor well area of the reactor. Earlier work at this reactor unit found a highly contaminated reactor well differential pressure line outside of containment. Our reporting on that can be found here.

The inspection inside the reactor well found some significant new findings. The edge of the containment cap is black and charred. Different from the rusty and general corrosion found on the unit 1 containment cap. The containment cap is a know likely failure route for reactor containment in a severe accident. The bolts that hold down the containment cap can elongate due to high pressure and high heat. The silicone seal for this cap has a maximum temperature rating of 620 f (320 c). Evidence of this type of failure was found at units 2 and 3 during the initial disaster and on later inspections at unit 1.

Unit 2 did not suffer a hydrogen explosion. This was likely due to the blow-out panel being dislodged prior to unit 2’s final failures. Unit 2 had a massive plume of highly radioactive steam out of this blow-out panel for weeks after the initial meltdown. In 2012 there was still a plume of steam escaping out of the reactor well.

fukushima unit 2 steam from meltdown

 

This refueling floor has been off-limits to workers since the initial disaster due to high radiation levels and microparticles of fuel spread around the area. In 2021 TEPCO puts a probe into the reactor well consisting of a camera, radiation meter, and light. The radiation levels are not incredibly high compared to some earlier readings found at the three damaged reactors but it is now almost 11 years post-meltdown, these levels have significantly reduced compared to what they would have been in 2011.

fukushima daiichi unit 2 reactor well radiation readings 2021

This series of images below show the charred damage to the flange of the containment cap.

fukushima unit 2 reactor well 2021

Outer reactor well wall (above). This was originally polished stainless steel.
This reference photo from unit 1 prior to the 2011 disaster shows what this area used to look like.

unit 1 fukushima daiichi reactor well pre disaster

 

The image below shows the reactor well wall and the underside of the concrete reactor well cover.

 

The image below shows another angle of the reactor well wall and the underside of the concrete reactor well cover.

 

The image below shows a close-up of the containment cap flange and bolts. Heavy dark charring can be seen on the flange.

 

This pair of images below show the side of the containment cap and the flange area. The cap is heavily corroded and charred at the flange.

 

The pair of images below show a further close-up of the charred flange.

 

This pair of images below shows a closer look at the charred flange. Some concrete spalling can be seen on the bulkhead.

 

So where is that fatal design flaw? The differential pressure line was mentioned earlier in this report. This line connects into the ductwork for the air conditioning and building ventilation system. Under normal operation, this would pull any potentially contaminated air into the ductwork and out via the filtered ventilation system. Under severe accident conditions, this created a direct route from inside containment to the reactor well, into the ductwork. TEPCO had previously cited hydrogen circulating through the ductwork of the reactor buildings as the likely cause for extensive building damage from the hydrogen explosions. The leaking containment cap provides the means for the radioactive gasses, vaporized fuel, and hydrogen to further escape into the building. Unit 2 did not suffer a hydrogen explosion as units 1 and 3 did. This has been assumed to be due to the dislodged blow-out panel giving a route for hydrogen to escape the building, keeping the total hydrogen concentrations below the threshold where they would be combustible.

TEPCO describes the differential line here:
“A line that adjusts the differential pressure between the reactor cavity (reactor well) and the operation floor during operation, connected to the exhaust duct of the reactor building ventilation and air conditioning system”

 

This information helps confirm that unit 2 did have a major event related to the meltdown at that unit via the containment cap. Unit 1 did not have
damage to this degree. Unit 3 has not had the reactor well inspected to date.

New images were sourced from TEPCO.
A machine translation of the TEPCO handout in English can be found here.
The original document in Japanese can be found here.

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: