TEPCO injected cement near parts of section 1 of the frozen wall on June 8.

South sections of the frozen wall near unit 4 are still struggling to freeze. TEPCO has not announced a specific response plan.

The sections near unit 1 appear to have been where the cement was injected but it is not clear if it has had a direct impact on this section. This section has seen some improvement over previous reports.

Many of the red and yellow sections have seen some cooling.
frozen_wall_section1_6_14_16
Latest report in English
Latest report in Japanese

 

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: