Fukushima Unit 1 Cover Removal Completed

unit1_cover_removal_161110_02TEPCO has reported that the last sections of the cover over unit 1 have been removed. The next phase is expected to be removal of the roof debris from the top refueling floor.

Through the process of removing the cover panels there have been multiple boundary dust monitor alarms at the plant. Each time TEPCO claimed the wind was blowing from offsite and that the only contaminant found was bismuth 214. This seemed unlikely considering the high levels of contamination outside the plant grounds from the disaster.

 

unit1_cover_removal_161110_03

This article would not be possible without the extensive efforts of the SimplyInfo research team
Join the conversation at chat.simplyinfo.org

© 2011-2023 SimplyInfo.org, Fukuleaks.org All Rights Reserved Content cited, quoted etc. from other sources is under the respective rights of that content owner. If you are viewing this page on any website other than http://www.simplyinfo.org (or http://www.fukuleaks.org) it may be plagiarized, please let us know. If you wish to reproduce any of our content in full or in more than a phrase or quote, please contact us first to obtain permission.

Editor

Editor, SimplyInfo.org

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: