1254 Fuel Assemblies Removed From Fukushima Unit 4
TEPCO reported that as of September 16, 2014 they have removed 1254 fuel assemblies from unit 4’s fuel pool. This
Read moreTEPCO reported that as of September 16, 2014 they have removed 1254 fuel assemblies from unit 4’s fuel pool. This
Read moreTEPCO is reporting that the console portion of the refueling machine that fell into the spent fuel pool of unit 3
Read moreA brief note in the daily reports mentioned that TEPCO will be pausing cooling to the unit 3 spent fuel
Read moreTEPCO announced that work to remove spent fuel from the unit 4 fuel pool will be suspended for 3 months.
Read moreTEPCO submitted plans to the NRA for spent fuel removal from unit 3. This included more detail on how they
Read moreThere are 411 spent fuel assemblies left to remove from unit 4 at Fukushima Daiichi. 1122 have been removed as
Read moreTEPCO is asking for permission to make an unusual change to the removal of spent fuel at unit 4. The
Read moreTEPCO has progressed on removing debris from the unit 3 spent fuel pool. The current work is to dismantle the
Read more968 fuel assemblies have been removed from the unit 4 spent fuel pool to the common pool. http://www.tepco.co.jp/en/decommision/index-e.html This article
Read more924 fuel assemblies have been removed from the spent fuel pool of unit 4 and placed into the common pool
Read more880 fuel assemblies have been removed from unit 4 to the common pool as of Monday. http://www.tepco.co.jp/en/decommision/index-e.html This article would
Read moreThe entire decommissioning plan has hinged on this one thing, the ability to flood the containment structures of the reactors
Read moreDon’t pop the champagne quite yet. Removal of spent fuel from the damaged unit 4 fuel pool has crossed the
Read moreSpent fuel processing at Fukushima has made some new progress though much work remains with higher risk work being left
Read more704 fuel assemblies have been removed from the unit 4 spent fuel pool to the common pool as of this
Read more638 spent fuel assemblies have been removed from the unit 4 spent fuel pool to the common pool as of
Read more594 fuel assemblies have been removed to the common pool from unit 4’s spent fuel pool. http://www.tepco.co.jp/en/decommision/index-e.html This article
Read moreTEPCO has accomplished some debris removal from the spent fuel pool as documented in this report. Earlier in 2014 work
Read more528 fuel assemblies have been moved to the common pool from unit 4’s spent fuel pool as of yesterday. This
Read more374 fuel assemblies have been moved from unit 4’s spent fuel pool to the common pool as of this week.
Read moreTEPCO reports a total of 352 fuel assemblies have been removed from the unit 4 spent fuel pool as of
Read more308 assemblies have been removed from the unit 4 spent fuel pool. The assemblies were transferred to the common pool
Read more264 fuel assemblies have been removed to the common pool from unit 4. http://www.tepco.co.jp/en/nu/fukushima-np/removal4u/index-e.html This article would not be possible
Read moreTEPCO announced late yesterday that another round of fuel assemblies was removed from unit 4 to the common pool at
Read moreTEPCO’s weekly update on fuel removed from Unit 4’s spent fuel pool now sits at 176 spent assemblies removed from
Read moreAnother cask of spent fuel has been transferred to the common pool from unit 4 at Fukushima Daiichi. This makes
Read moreTEPCO reports as of November 30, 2013 JST the second set of 22 fuel assemblies were loaded into the fuel
Read moreKyodo News announced yesterday that preparations are underway to remove the debris from the unit 3 spent fuel pool at
Read moreTEPCO announced an additional 16 spent fuel assemblies were loaded into the transport cask by the end of the day
Read moreTEPCO announced work to begin taking out spent fuel at unit 4 resumed this Wednesday morning JST. http://www.tepco.co.jp/cc/press/2013/1232461_5117.html This
Read moreTEPCO has announced that 6 fuel assemblies have been removed from the pool racks to the transport cask by the
Read moreNHK is reporting that TEPCO will continue the process to remove spent fuel from the unit 4 pool on Tuesday
Read moreTEPCO announced they have removed the first load of fuel from unit 4 to the racks in the common pool.
Read moreNHK and TEPCO have announced that the first cask of fuel assemblies has been moved from unit 4 to the
Read moreNHK is reporting that the cask transport effort took place Wednesday day. TEPCO has not forwarded any additional announcements at
Read moreTEPCO announced that they have filled the first cask with fuel as of 6:28PM JST Tuesday. A total of 22
Read moreTEPCO has released photos of the first fuel successfully removed from the fuel racks at unit 4. NHK reports the
Read moreFrench journalist Joel Legendre is reporting that TEPCO will begin removing the first fuel assemblies from the spent fuel pool
Read moreNHK reports It is roughly 9:59am as this is being written. Workers at Fukushima Daiichi should have begun the process
Read moreThere are lots of concerns about the upcoming fuel removal work at unit 4. With this has come some passing
Read more